WATER WORKS AT BLACKBUTT

MEDIA RELEASE


Sydney Water contractor, Downer, will be upgrading the water supply facility located on Pioneer Drive, Blackbutt.

These works will improve the water system and help protect public health.

Work is scheduled to commence in early April and will take approximately 5 months to complete, weather permitting.

Upon completion of works, the site will have a new rechlorination building and equipment, truck turn around bay and delivery bund. Grassed areas affected by the work will be reinstated.

All efforts will be made to minimise disturbance whilst the required works are carried out, however local residents may notice an increase in personnel, dust and temporary construction noise.

Traffic management will be in place during different stages of the work. Work hours will be 7am to 6pm, Monday to Friday, and 8am to 1pm on Saturdays, if required.

Water and wastewater services will not be affected.

 

22 March 2017